Build Order Exists

MediumGraphsPython, JavaScript, TypeScript, Java, C++

A project has n build steps numbered 0 to n - 1. before is a list of pairs [a, b] meaning step a must be completed before step b can start. The same pair may appear more than once.

Return true if all n steps can be arranged in one sequence that respects every pair, and false if the requirements contradict each other. With no pairs the answer is true.

Example 1

n 3
before [[0,1],[1,2]]
returns true

The order 0, 1, 2 respects both pairs.

Example 2

n 3
before [[0,1],[1,2],[2,0]]
returns false

Step 0 must come before 1, 1 before 2, and 2 before 0, which is impossible.